TPC Installation and Commissioning Meeting

CERN, 17 February 2006

______________________________________________________

 

Agenda

  1. FEE Installation and Commissioning (L. Musa)

  2. First Results on Electronics Tests (Rok Pestotnik and Stefan Kniege)

  3. FEE Configuration (R. Bramm)

  4. DCS & Communication Software for FEE (D. Roherich)

  5. Status of DCS board and Configuration Scheme for the RCU (J. Alme)

  6. The New H-RORC (T. Alt)

  7. HLT TPC Online Monitoring (J. Thader)

  8. DAQ & ECS Systems for TPC Commissioning (F. Carena and P. Vande Vyvre)

  9. TPC FEE Calibration (R. Bramm)

  10. Offline framework for conditions data (L. Betev)

  11. Meeting minutes (L. Musa)
     

___________________________________________________

TPC Installation and Commissioing Meeting

CERN, 22 November 2005

______________________________________________________

 

Agenda

  1. FEE Installation and Commissioning I (L. Musa)

  2. FEE Configuration & Expert Online Monitor (R. Bramm)

  3. FEE Installation and Commissioning II (L. Musa)

  4. Detector Control System (U. Frankenfeld)

  5. DCS & Comunication Software for FEE (S. Bablok)

  6. DAQ & ECS Systems for TPC Commissioning (K. Schossmaier)

  7. TPC Commissioning - HLT Aspects (M. Richter)

  8. TPC Calibration (M. Kowalski)

  9. TPC Calibration with laseer tracks (B. Nielsen and G. Renault)

  10. Meeting minutes (M. Ivanov)
     

 

 

______________________________________________________

TPC FEE Collaboration Meeting

Bergen, 07 April 2005

______________________________________________________

 

Agenda

Thursday 07 (9:00 - 18:00)

(I) Action list from last TPC Meeting (L. Musa)

(I) RCU Review

bullet

Hardware

- RCU Characterization (L. Musa for B. Mota)

- Mass Production and Test (R. Campagnolo)

- DDL-SIU Status  (C. Soos)

bullet

Firmware

- Slow Control (C. Gonzalez)

- FPGA Reconfiguration (G. Tröger)

- FPGA Reconfiguration (K. Roed)

(II) Software

- DCS (M. Richter)

- HLT Monitor (T. Steinbeck)

(III) Preparation of the Irradiation Tests at Uppsala

Organization (K. Roed)

FECs Setup (L. Musa)

 

______________________________________________________

TPC FEE Collaboration Meeting

CERN, 13-14 January 2005

______________________________________________________

 

Agenda

Thursday 13 (9:00 - 18:00)

(I) RCU Review

bullet

Hardware

- Schematic Design (K. Ullaland)

- Layout Requirements (L. Musa)

- PCB Layout  (A. Junique)

bullet

Firmware

- Dataflow (B. Mota)

- Slow Control (C. Gonzalez)

- Trigger Interface (J. Alme)

- FPGA Reconfiguration (J. Alme)

- Firmware for the Auxiliary FPGA (J. Alme)

- Firmware for the DCS (J. Alme)

bullet

Software

- RCU DDL (B. Mota)

- RCU DCS (M. Richter)

- DCS (S. Bablok)

- Trigger Interface (D. Rohrich)

(II) Online Monitor

- Pad Monitor (R. Bramm)

- Pad Monitor (K. Shossmaier)

- HLT Monitor (D. Rohrich)

- HLT Monitor (M. Richter)

Friday 14 (9:00 - 12:00)

(III) Preparation of the Irradiation Tests at Uppsala

Radiation Tests (D. Rohrich)

Radiation Tests (K. Roed)

(IV) System Pre-commissioning (R. Campagnolo)

(V) ALTRO chips for PHOS (L. Ostermann)

 
 
 
 
 